1. HOLE PREPARATION: Concrete, Brick, Hollow and Grout-Filled CMU

For horizontal, vertical and overhead applications.

Step 1 Step 2 Step 3 Step 4
1. Drill - Drill hole to specified diameter and depth. 2. Blow - Remove dust from hole with oil-free compressed air for a minimum of 4 seconds. 3. Brush - Clean with a nylon brush for a minimum of 4 cycles. 4. Blow - Remove dust from hole with oil-free compressed air for a minimum of 4 seconds.

2 . CARTRIDGE PREPARATION: For AT, SET, ET and ETF


1. Check - Check cartridge expiration date. Do not use expired product. Product is usable until end of printed expiration month. 2. Open - Open cartridge per package instructions. Step 3 Step 4 Step 5
4. Insert - Attach proper Simpson nozzle to cartridge. Do not modify nozzle. 5. Dispense - Dispense adhesive to the side until properly mixed (uniform color).
3. Attach - Attach proper Simpson nozzle to cartridge. Do not modify nozzle.

3. FILLING THE HOLE: Vertical Anchorage

Prepare the hole per instructions "Hole Preparation".

Dry and Damp Holes: Step 1 1. Fill - Fill hole 1/2 - 2/3 full, starting from bottom of hole to prevent air pockets. Withdraw nozzle as hole fills up. Step 2 2. Insert - Insert clean, oil free anchor, turning slowly until the anchor contacts the bottom of the hole. Step 3 3. Do not disturb - Do not disturb anchor until fully cured. (See cure schedule for specific adhesive.)
Water Filled Holes: (SET or AT only) Step 1 1. Fill - Fill hole completely full, starting from bottom of hole to prevent water pockets. Withdraw nozzle as hole fills up. Step 2 2. Insert - Insert clean, oil free anchor, turning slowly until the anchor contacts the bottom of the hole. Step 3 3. Do not disturb - Do not disturb anchor until fully cured. (See cure schedule for specific adhesive.)

3. FILLING THE HOLE: Horizontal and Overhead Anchorage: For AT, SET, ET and ETF

Prepare the hole per instructions "Hole Preparation".

Step 1 Step 2 Step 3 Step 4
1. Install - Install Simpson ARC adhesive retaining cap (recommended). 2. Fill - Fill hole 1/2 - 2/3 full, starting from bottom of hole to prevent air pockets. Withdraw nozzle as hole fills up. 3. Insert - Insert clean, oil free anchor, turning slowly until the anchor contacts the bottom of the hole. 4. Do not disturb - Do not disturb anchor until fully cured. (See cure schedule for specific adhesive.)

3. FILLING THE HOLE: When Anchoring with Screens: For AT, ET, and SET (except SET1.7KT or SET1.7KTA)

Prepare the hole per instructions "Hole Preparation".

Step 1 Step 2 Step 3 Step 4
1. Fill - Fill screen completely. Fill from the bottom of the screen and withdraw the nozzle as the screen fills to prevent air pockets. (Opti-Mesh screens: Close integral cap after filling.) 2. Insert - Insert adhesive filled screen into hole. 3. Insert - Insert clean, oil free anchor, turning slowly until the anchor contacts the bottom of the screen. 4. Do not disturb - Do not disturb anchor until fully cured. (See cure schedule for specific adhesive.)

3. FILLING THE HOLE: VGC Vinylester Glass Capsule (Hammer Capsule)

Prepare the hole per instructions "Hole Preparation".

Step 1 1. Insert - Insert the VGC capsule(s) to the bottom of the hole (either end first). Step 2 2. Install - Install double nut to protect thread. Step 3 3. Drive - Drive stud or rod to the bottom of the hole. Spinning of the stud or rod is not required. Step 4 4. Do not disturb - Do not disturb anchor until fully cured. (See cure schedule for VGC.) VGC is not recommended for overhead applications.